|
Query No.
29
Subject:
Accounting for construction
contracts under percentage
of completion method.1
A. Facts of the
Case.
1. A company has been
undertaking civil engineering contracts for the last three decades. According to the querist, the company
recognises income based on percentage completion method as per Accounting
Standard (AS) 7, ‘Accounting for Construction Contracts’. The maximum tenure of the company’s
projects is about 3 years and it is in a position to determine the profit/loss
of a project with reasonable certainty even at the time of receiving the order
itself. All the company’s contracts
are fixed price contracts, some of which have escalation
clauses.
2. The company recognises
income (turnover) as and when the bills are certified by its clients
irrespective of the fact whether the payment is received or not. Similarly, the expenses are accounted
for as and when the liability is incurred irrespective of the fact whether the
payment is made or not. As per the
querist, the company, in accordance with paragraph 9.8 of AS 7, has a policy not
to recognise profit or loss from a project unless a minimum of 20% of the total
project value is completed.
3. Thus, the company
recognises profit only on completion of atleast 20% of the total value of the
contract. As per the querist, the
profit or loss in respect of the whole project is determined after taking into
account the following as specified in paragraph 9.6 of AS 7:
(i) The
income in respect of work done for a project is accounted for based on the bills
certified by the client.
(ii) The
expenditure is accounted for as and when the liability is
incurred.
(iii) Future
estimated cost to complete the project.
(iv) Future
estimated billing till the completion of the project.
The overall profit or loss of the project is
estimated after taking into account the above factors. The profit/loss is then arrived at as a
percentage of the total value of the project. The expected profit/loss percentage thus
arrived at is applied to the overall work done upto the end of the financial
year and the quantum so arrived at is shown as profit or loss as the case may
be.
4. As per the querist, by
employing this method, the company not only recognises the profit/loss of a
project uniformly over different financial years but also takes the advantage of
percentage completion method by way of reflecting income to the extent of work
actually executed as stated in AS 7.
5. If the difference
between the income and the expenditure for any financial year for a given
project on a percentage basis is more than the overall expected profit
percentage as calculated in the manner explained above, then that percentage of
excess amount is transferred from the actual billing certified by the client to
current liability and shown as advance payment received from the clients. As per the querist, this entry is passed
in accordance with paragraphs 15.2 and 9.3 of AS 7.
6. However, where the
difference between income and expenditure on a percentage basis as calculated
above is less than that of overall profit percentage basis at the end of
financial year, the difference is either adjusted from expenses which are in the
nature of deferred revenue or shown as closing WIP depending on the project
realities.
7. As per the querist,
progress payments and advances received from customers which are not in relation
to work performed are shown as liability in accordance with paragraph 15.2 of AS
7. Similarly, amount retained by
customers towards satisfactory performance is shown as receivable in accordance
with paragraph 15.3 of AS 7.
B. Queries
8. Keeping the above in
view, the querist has sought the opinion of the Expert Advisory Committee on the
following issues in reference to certain paragraphs of AS 7:
(i) According to paragraph 9.1 of AS 7, the advantage of percentage
completion method of accounting is that it reflects revenue in the accounting
period during which activity is undertaken to earn such
revenue.
(a)
Accordingly, whether in fixed price contracts, the actual value of work
certified can be accounted for as income (turnover) irrespective of whether the
work has progressed to a reasonable extent (i.e., 20% in the case of the
company).
(b) In
order to give effect to the advantage as contemplated in paragraph 9.1 of AS 7,
whether the work done but not certified as well as work done not billed can also
be accounted for as income (turnover).
(ii) According
to paragraph 9.2 of AS 7, in order to determine revenue, no special weightage
should be given to any single factor; instead, all factors should be taken into
consideration. Further, according
to paragraph 9.3, progress payments and advances received from customers cannot
usually be treated as equivalent to revenue earned.
Thus, if progress payments are received in such a manner that they do not
reflect the actual percentage of work done but such progress payments are made
purely to honour contractual terms, then whether it would be appropriate to
recognise the same as income (turnover) irrespective of the fact that such
payments are based on the running bills raised by the company and certified by
the client.
The querist has stated that the abovesaid situation does arise in certain
cases where a higher ‘unit rate’ is bid for all items of initial work and a
lower ‘unit rate’ is bid for later work and consequently cash inflow of the
project in the initial period would be disproportionately higher and, similarly,
the cash inflow at the final stages of the project would be disproportionately
lower.
(iii) According
to paragraph 9.8 of AS 7, normally, the profit is not recognised under fixed
price contracts unless the work on a contract has progressed to a reasonable
extent.
(a)
Whether only the profit should not be recognised till the project has
reasonably progressed or even the income (turnover) should not be
recognised.
(b) In
case the income (turnover) is also not to be recognised, then what is the
justification of stating in paragraph 9.1 of AS 7 that a contractor is allowed
to take the advantage of reflecting the revenue of actual work
performed.
(c) In
case the income (turnover) is allowed to be recognised and the expenditure in
respect of the project upto the end of the year is either more or less than that
of the income upto the end of the year, then how should the difference be
treated? In other words, if the
income (turnover) is more than the expenditure, whether the excess amount can be
treated as liability by transferring the excess amount from income to advance
received from client and show a no-profit, no-loss situation. Similarly, if the expenditure is more
than the income then whether the difference can be treated as deferred
expenditure or by way of increase in WIP to the extent of difference and still
show a no-profit, no-loss situation.
C. Points Considered by the
Committee
9. The Committee notes the
following paragraphs of Accounting Standard (AS) 7, ‘Accounting for Construction
Contracts’:
“9. Percentage of
Completion Method
9.1 Under the percentage of
completion method, the amount of revenue recognised is determined by reference
to the stage of completion of the contract activity at the end of each
accounting period. The advantage of this method of accounting for contract
revenue is that it reflects revenue in the accounting period during which
activity is undertaken to earn such revenue.
9.2 The stage of completion
used to determine revenue to be recognised in the financial statements is
measured in an appropriate manner. For this purpose no special weightage should
be given to a single factor; instead, all relevant factors should be taken into
consideration; for example, the proportion that costs incurred to date bear to
the estimated total costs of the contract, by surveys which measure work
performed and completion of a physical proportion of the contract
work.
9.3 Progress payments and
advances received from customers may not necessarily reflect the stage of
completion and therefore cannot usually be treated as equivalent to revenue
earned.”
“9.5 The application of the percentage of completion method is subject to a
risk of error in making estimates. For this reason, profit is not recognised in
the financial statements unless the outcome of the contract can be reliably
estimated. If the outcome cannot be reliably estimated, the percentage of
completion method is not used.
9.6 While recognising the
profit under this method, an appropriate allowance for future unforeseeable
factors which may affect the ultimate quantum of profit is generally made on
either a specific or a percentage basis.
9.7 In the case of fixed
price contracts, the conditions which will usually provide this degree of
reliability are:
(i)
total contract revenues to be received can be reliably
estimated;
(ii)
both the costs to complete the contract and the stage of contract
performance completed at the reporting date can be reasonably estimated;
and
(iii) the
costs attributable to the contract can be clearly identified so that actual
experience can be compared with prior estimates.
9.8 Normally, the profit is
not recognised in fixed price contracts unless the work on a contract has
progressed to a reasonable extent. Ordinarily, this test is not considered as
having been satisfied unless 20 to 25% of the work is
completed.”
10. The Committee notes that as per paragraph 9.2 of AS 7, the revenue to be
recognised is determined by reference to the stage of completion of the contract
activity as determined on the basis of the relevant factors.
11. The Committee is of the view that AS 7 contemplates recognition of all
expenditures pertaining to the stage of construction reached at the end of the
financial year, and the recognition of revenue by applying the percentage of
work completed to the total contract value. Thus, the profit figure for the period
is the difference between the revenue so recognised and the costs incurred for
completing the project upto that stage, subject to allowance as per paragraph
9.6 of AS 7, as reproduced above.
In other words, it is the actual profit so arrived at which should be
recognised rather than the profit figure based on the overall profit percentage
as worked out by the company.
Further, the billing pattern would not have any effect on the revenue
recognition unless it represents the actual work completed. Any excess or short billing would be
reflected as advance received or amounts receivable as the case may
be.
12. From the above, the Committee is of the view that the company’s
accounting system as stated in the facts is not in accordance with AS
7.
13. The Committee is also of the view that the conditions stipulated in
paragraph 9.7 of AS 7 for recognition of profit are usually not considered as
having been satisfied unless 20% to 25% of the work has been completed. This is so because it is normally
considered too early for any project to say with reliability that the project
will be profitable. Since the major
portion of the construction work is yet to be completed, keeping in view the
contingencies that may arise in future, it is considered prudent not to
recognise any profit at that early stage.
At the end of the financial year, the cost of such work completed which
is less than 20-25%, should be carried over as
work-in-progress.
D. Opinion
14. On the basis of the above, the Committee is of the following opinion on
the issues raised in paragraph 8:
(i) (a) Ordinarily, in a fixed
price contract, the profit is not recognised unless the work has progressed to a
reasonable extent (i.e., 20% to 25%).
Therefore, revenue (turnover) is not recognised in the financial
statements. The cost of such work
done is carried over to the next period as
work-in-progress.
(b)
No. Please refer to
paragraph 11 above.
(ii) No. Please refer to paragraph 11
above.
(iii) (a) The revenue (i.e. turnover) should also
not be recognised in the financial statements.
(b)
Please refer to paragraph 13 above.
(c) In
view of what has been stated above, this issue does not arise.
1Opinion finalised by the Committee on
25.9.2000.
|