Expert Advisory Committee

ICAI-Expert Advisory Committee
Options:

Query No. 25

 

Subject:          

  Accounting for borrowing costs.1

 

A. Facts of the Case

 

1. A public limited company is engaged in the production of fertilisers for the last five years. The company has recently set up a new plant at a different location for the manufacture of Di Ammonia Phosphate (DAP), a different fertiliser, with annual capacity of 19.2 lakh tons equivalent to1.6 lakh tons per month. Cost of the project is around Rs. 2500 crore and has been financed through loans from various financial institutions/banks to the tune of Rs.1600 crore and the balance amount has been financed through internal accruals.

 

2. The production process is carried on in three sub-plants. In the first two sub-plants, raw materials are manufactured to be used ultimately in the manufacture of final product in the third sub-plant. The raw materials manufactured in the first two sub-plants can alternatively be purchased from  other  sources  and  used  for  manufacturing  the  final  product.  The final  sub-plant  has  three  machines  wherein  the  final  product  can  be manufactured in any or all of the machines depending on the production plan. The  final sub-plant has  been handed over  to the company by the consultants in September 2000. However, two intermediary plants are yet to be handed over to the company by the plant consultants. As per the agreement with the manufacturers, there is a requirement of Guarantee Test (GT)/Performance Test (PT) of 72 hours before acceptance of the plant, subject to satisfactory results. On sub-plant one, 72 hours GT/PT, though started during March 2000, had not been completed on the date of sending the query. On sub-plant two GT/PT was conducted on October 7-9, 2000 and after evaluation of test data, sub-plant two was accepted on  October 16,  2000. Out  of the  three  machines in  sub-plant three,  on machine I, GT/PT was conducted during October 7-9, 2000 and accepted on October 16,  2000 and on machine II, GT/PT  was conducted during May 22-24, 2000, and accepted on October 16, 2000. However, on machine III, GT/PT was waived off by the company and accordingly, no GT/PT was carried out on machine III. In between, the company had faced some technical problems with its intermediary plants resulting into fluctuation in the quantity of DAP produced on month to month basis. The company is undergoing trial production with effect from March 23, 2000 and DAP produced  by it  is  well  accepted  in  the  market.  The  company produced 5.23 lakh tons of DAP and sold around 4.97 lakh tons at normal selling price till November 2000 and there is no difficulty in selling out DAP produced by its new plant. The month-wise break-up of quantity produced and sold, for the year 2000, is given below:

 

Month  Quantity of DAP           Quantity of DAP

            produced (Tons)           sold (Tons)

 

March          9,339                       NIL

April             32,614                     739

May             75,213                      8,907

June             29,781                      27,478

July              80,870                      65,009

August          87,788                     85,201

September     26,596                 1,02,222

October        119,557                 79,018

November      61,056                 128,589

 

3. The borrowing cost for financing the said project is around Rs. 400 crore.  The  company  had  also  taken  working  capital  loans  to  fund  the costs  of  production  during  the  said  trial  run.  The  cost  of  the  said borrowings is around Rs. 150 crore and the value of the sale is around Rs. 500-600 crore.

 

4. According  to  the  querist,  paragraph  11  of  the  ‘Guidance  Note  on Treatment  of  Expenditure  During  Construction  Period’  (hereinafter referred to as the ‘Guidance Note’) states that as a general rule it would be proper to capitalise all expenses incurred for start-up and commissioning of the plant. The querist has referred to the last two sentences of paragraph 12.2 of the Guidance Note which are reproduced below:

 

“Even during a period of test runs and experimentation, a plant may be engaged in actual production, but until the test runs are completed and the plant is properly adjusted on the basis thereof, it may not be said to be ready for “commercial production”. The term “commercial production” refers to production in commercially feasible quantities and in a commercially practicable manner.”

 

5. The company is expecting to streamline its production process and to overcome all the technical problems within next two to three months and it is expected that the plant will be able to achieve desired level of production  of  DAP on  monthly basis. Accordingly,  all  activities  in  the nature  of  testing  and  adjusting  the  plant  (with  the  sub-plants)  for commercial  production  will  be  performed/completed.  The  company contends that usually in the fertiliser industry, all plants run at 100% or higher  capacity  utilisation  and  in  view  of  the  facts  mentioned  above including  significant  fluctuations  in  the  monthly  production,  the  plant cannot be said to have been put to its intended use. As per the querist, in the  view  of  the  company,  the  plant  can  only  be  said  to  be  put  to  its intended use once it achieves a consistently high level of production (say 80% of installed capacity).

 

6.  As per the querist, the process of aligning capacities and production that  is  in  progress  at  the  trial  run  stage,  is  not  routine  administrative work. Therefore, the plant cannot be described to be ready for its intended use  (i.e.,  “production  in  commercially  feasible  quantities  and  in  a commercially practicable manner”) and interest cost may, therefore, be capitalised.

 

7. According  to  the  querist,  as  per  paragraph  12.4  of  the  Guidance Note,  if  a  plant  is  completed  and  commissioned  and  is  ready  for commercial production, but for some reason does not start commercial production  immediately  thereafter,  the  expenditure  incurred  during  the intermediate  period  must  be  treated  as  revenue  expenditure  and  not capitalised,  provided  the  delays  were  not  inordinate  and  in  such  cases related interest costs may be amortised over 3 to 5 years. In the view of the querist, as per paragraph 4.3 of the Guidance Note, interest on working capital  facilities  incurred  during  construction  period  is  to  be  carried forward  in  the  balance  sheet  under  the  heading  “Miscellaneous Expenditure”  to  be  subsequently  written  off  to  profit  and  loss  account after  the   commencement  of  commercial  production  over  a  period  not exceeding 3 to 5 years. However, such expenditure is normally charged to revenue.

 

8. According to the querist, under the aforementioned circumstances, wherein the commercial production is considerably delayed, in the light of the recommendations set out in paragraph 13.4 of the Guidance Note, such  interest  expenditure  may  be  treated  as  part  of  deferred  revenue expenditure to be amortised over a period not exceeding 3 to 5 years.

 

9. The  querist  has  referred  to  paragraphs  6  and  14  of  Accounting Standard (AS) 16, ‘Borrowing Costs’, which are reproduced below:  

“6. Borrowing costs that are directly attributable to the acquisition, construction or production of a qualifying asset should be capitalised as  part  of  the  cost  of  that  asset.  The  amount  of  borrowing  costs eligible for capitalisation should be determined in accordance with this  Statement.  Other  borrowing costs should  be  recognised  as  an expense in the period in which they are incurred.”  

“14. The capitalisation of borrowing costs as part of the cost of a qualifying asset should commence when all the following conditions are satisfied:

 

(a)        expenditure for the acquisition, construction or production of a qualifying asset is being incurred;

 

(b)        borrowing costs are being incurred; and

 

(c)        activities  that  are  necessary to  prepare  the  asset  for  its intended use or sale are in progress.”

10. The querist has also referred to paragraph 19 of AS 16 which requires that “capitalisation of borrowing costs should cease when substantially all the activities necessary to prepare the qualifying asset for its intended use or sale are complete”. The Standard also mentions that “an asset is normally ready for its intended use or sale when its physical construction or production is complete even though routine administrative work might still continue” (paragraph 20).

 

B. Queries

 

11. The querist has sought the opinion of the Expert Advisory Committee on the following issues:

 

(a)        Whether, in view of the facts mentioned above, the aforesaid period (i.e., the period starting from March 23, 2000 till date/ the  date  of  declaration  of  commercial  production)  can  be considered as the period of trial run and accordingly whether it  can  be  considered  that  assets  have  not  been  put  to  their intended use.

(b)        If the answer to (a) above is in the affirmative, (i.e., the period starting from March 23, 2000 till date/the date of declaration of commercial production is considered as the period of trial run), whether, in view of paragraphs 14 and 19 of AS 16 and paragraphs  11,  12.4  and  13.4  of  the  Guidance  Note,  the borrowing  costs  incurred  for  the  said  period  in  respect  of financing the DAP plant can be capitalised.

 

(c)        If  the  answer  to  (a)  above  is  in  the  negative,  in  view  of paragraph  4.3  of  the  Guidance  Note,  whether  the  borrowing costs  incurred  during the  said  period  in  respect  of  financing the DAP plant can be treated as deferred revenue expenditure to be amortised over 3-5 years.

 

(d)        In view of paragraph 4.3 of the Guidance Note, whether the interest paid on the funds borrowed for working capital during the said period can be treated as deferred revenue expenditure to be amortised over 3-5 years.

 

(e)        If the answer to (d) above is in the negative, whether the same can be recognised as an expense in the said period in view of paragraph 6 of AS 16.

C.        Points considered by the Committee

 

12. The Committee notes that according to the querist, trial production has  started  with  effect  from  23rd  March,  2000  and  that  till  the  date  of sending  the  query  the  trial  production  was  continuing. Accordingly,  it appears from the facts that according to the querist, the plant is not ready to commence commercial production. Keeping in view the issues raised by the querist, the Committee notes that the query relates to treatment of borrowing costs incurred during the period after the start of the trial runs.

 

13. The Committee notes paragraphs 11.2, 11.4, 12.2, 12.4 and 13.4 of the  Guidance  Note  on  Treatment  of  Expenditure  During  Construction Period,  issued  by  the  Institute  of  Chartered  Accountants  of  India, reproduced below:  

“11.2  As  a  general  rule,  it  would  be  correct  to  capitalise  all expenses  incurred  during  this  period  and  in  connection  with  the process of start-up and commissioning of the plant, for two reasons. In the first place, such expenses would be incurred in order to bring the  plant  up  to  the  stage  at  which  it  can  commence  commercial production. In the second place, this expenditure would normally be incurred before the plant is taken over. On both these considerations,it would be fair and correct to capitalise the expenditure incurred on start-up and commissioning the plant. The expenditure so incurred may be capitalised  in the same way as  other indirect construction expenditure.”  

“11.4    During the period of test runs and experimental production it is quite possible that some income will be earned through the sale of  the  merchandise  produced  or  manufactured  during  this  period. The sale revenue should be set off against the indirect expenditure incurred during the period of test runs and treated as suggested in para 15.2.”  

“12.2    In several cases, guidance may be available in selecting the official date of commencement of production by reference to the date  of  the  inauguration  ceremony  as  well  as  by  reference  to  the date which is publicly and officially announced by the company as the  date  on  which  it  has  commenced  commercial  production.  It should  be  borne  in  mind,  in  this  connection,  that  “commercial production” is a term of somewhat wider import than the mere term “production”. Even during a period of test runs and experimentation,a plant may be engaged in actual production, but until the test runs are completed and the plant is properly adjusted on the basis thereof,it  may  not  be  said  to  be  ready  for  “commercial  production”.  The term “commercial production” refers to production in commercially feasible quantities and in a commercially practicable manner.”  

“12.4    It  is  important  to  note  in  this  connection  that  what  is significant for this purpose is the date when the plant is ready for commercial  production  and  not  the  date  when  the  plant  actually commences commercial production. Therefore, if a plant had been completed and commissioned and is ready for commercial production, but the company for some reason or other, does not start commercial production immediately thereafter, the expenditure incurred during this intermediate period must be treated as revenue expenditure and cannot be capitalised. This follows from an important rule, both in accounting principle as well as in economic theory. The rule is that only those expenses should be capitalised as part of the cost of an asset which relate to the acquisition or construction of that asset or which  add  anything  to  the  value  or  utility  of  that  asset.  When  a plant  has  once  been  completed  and  is  ready  for  commercial production, the expenditure incurred during the intervening period of delay in actually commencing commercial production is neither related to the acquisition or construction of the fixed assets nor does it  add  to  the  value  or  utility  thereof    consequently,  it  must  be written off as revenue expenditure and cannot be capitalised.”  

“13.4 If commercial production is considerably delayed, the problem which  would  arise  is  that  there  would  be  no  income  during  the period of such delay while, on the other hand, the expenditure of a revenue nature incurred during this period would have to be charged to the profit and loss account as mentioned above. If the period of delay in commencing commercial production is extremely prolonged, the  only  possible  concession  which  may  be  made  is  that  the expenditure incurred during this period  can be treated as deferred revenue expenditure, to be amortised over a period not exceeding 3to 5 years after the commencement of commercial production. This procedure  is  not,  however,  recommended  as  a  matter  of  general policy or practice, but may be resorted to only in those exceptional cases where fairly heavy revenue expenditure is incurred during a prolonged period of delay in commencing commercial production. In any case, it would be completely wrong to treat such expenditure as capital expenditure since it does not add in any way to the value or  cost  or  utility  of  the  plant  and  other  manufacturing  facilities which have already been constructed but which have remained idle due to delay in commencing commercial production.”

 

14.   The  Committee  also  notes  paragraphs  9.4  and  9.5  of  Accounting Standard (AS) 10, ‘Accounting for Fixed Assets’, issued by the Institute of Chartered Accountants of India, which state as below:

 

“9.4  The expenditure incurred on start-up and commissioning of the project,  including  the  expenditure  incurred  on  test  runs  and experimental production, is usually capitalised as an indirect element of the construction cost. However, the expenditure incurred after the plant  has  begun  commercial  production,  i.e.,  production  intended for sale or captive consumption, is not capitalised and is treated as revenue expenditure even though the contract may stipulate that the plant  will  not  be  finally  taken  over  until  after  the  satisfactory completion of the guarantee period.

 

9.5   If the interval between the date a project is ready to commence commercial production and the date at which commercial production actually begins is prolonged, all expenses incurred during this period are charged to the profit and loss statement. However, the expenditure incurred  during  this  period  is  also  sometimes  treated  as  deferred revenue expenditure to be amortised over a period not exceeding 3 to 5 years after the commencement of commercial production.” 2

 

15.   The Committee notes that paragraphs 9.4 of AS 10 and 11.2 of the Guidance Note deal with accounting for costs (including interest costs) incurred  during  trial  run  prior  to  the  commencement  of  commercial production. Paragraph 12.2 of the Guidance Note describes when a plant can  be  considered  to  have commenced  “commercial  production”. Paragraph 9.5 of AS 10 and paragraphs 12.4 and 13.4 of the Guidance Note  are  relevant  where  the  plant  is  ready for  commercial  production, i.e.,  the  trial  run  is  over  but  the  commencement  of  the  commercial production has been delayed. The Committee also notes that paragraph 12.4 of the Guidance Note does not recommend that costs incurred should be deferred over a period of 3-5 years as stated by the querist in paragraph 7 of the query.

 

16.   The Committee also notes that paragraph 4.3 of the Guidance Note recommends, inter alia, the following treatment with regard to the interest on working capital incurred during construction period :  

“With  regard  to  interest  charges  and  commitment  fees  on  loans taken specially and exclusively for the purpose of providing working capital,.…., it will be more appropriate to transfer the interest charges and commitment fees during the period of construction to a separate account  which  is  carried  forward  in  the  balance  sheet  under  the group heading of “Miscellaneous Expenditure” until it is subsequently written-off  to  profit  and  loss  account  after  the  commencement  of commercial production, over a period not exceeding 3 to 5 years.”

 

17. The  Committee  notes  paragraphs  6,  14,  19  and  20  of  Accounting Standard (AS) 16, ‘Borrowing Costs’, issued by the Institute of Chartered Accountants of India, as stated in paragraphs 9 and 10 above.

 

18. The  Committee  is  of  the  view  that  duration  of  a  trial  run  and experimental  production  and  when  the  plant  is  ready  for  commercial production  is  based  on  factors  such  as  technological  evaluation  of  the readiness of the plant and machinery and other facilities, the quality and the  quantity  of  the  output  produced,  etc.  The  Committee  notes  that commercial  production  means  production  in  commercially  feasible quantities and in a commercially practicable manner. The Committee is of the view that in deciding the quantity of commercial production, the basic  consideration  is  that  the  quantities  produced  are  adequate  to  be sold  in  the  market.  Achievement  of  a  particular  level  of  capacity  may not, therefore, be the deciding criterion since the quantity of the production which can be commercially exploited in the market can be lower than the optimum  level  of  capacity  utilisation  of  the  plant.  The  Committee  is, therefore,  of  the  view  that  when  the  plant  is  ready  for  commercial production, is a question of fact which should be determined on the basis of the factors stated above. The Committee is further of the view that in this  regard,  what  is  relevant,  is  the  date  when  the  plant  is  ready  for commercial  production  and  not  the  date  when  the  plant  actually commences commercial production. Normally the period of trial run is not very long. Where the period of trial run gets prolonged due to abnormal reasons, abnormal period should not be considered as a part of the trial run period for capitalisation of expenditure.

 

19. The Committee notes that a Clarification on Status of Accounting Standards and Guidance Notes, published by the Institute of Chartered Accountants of India in April 2002 issue of the Journal ‘The Chartered Accountant’, states as below:

 

“In  a  situation  where  certain  matters  are  covered  both  by  an Accounting Standard and a Guidance Note, issued by the Institute of Chartered Accountants of India, the Guidance Note or the relevant portion thereof  will be  considered as superseded  from the  date of the relevant Accounting Standard coming into effect, unless otherwise specified in the Accounting Standard.Similarly,  in  a  situation  where  certain  matters  are  covered  by  a recommendatory  Accounting  Standard  and  subsequently,  an Accounting Standard is issued which also covers those matters, the recommendatory Accounting Standard or the relevant portion thereof will be considered as superseded from the date of the new Accounting Standard coming into effect, unless otherwise specified in the new Accounting Standard.

 

In  a  situation  where  certain  matters  are  covered  by  a  mandatory Accounting Standard and subsequently, an Accounting Standard is issued  which  also  covers  those  matters,  the  earlier  Accounting Standard  or  the  relevant  portion  thereof  will  be  considered  as superseded from the date of the new Accounting Standard becoming mandatory,  unless  otherwise  specified  in  the  new  Accounting Standard.”

 

20. The Committee notes that AS 16 is mandatory in nature in respect of accounting periods commencing on or after 1-4-2000. The Committee also  notes  that  once  an  accounting  standard  becomes  mandatory,  any treatment  in  this  regard  recommended  in  a  guidance  note/statement automatically stands  withdrawn. The  Committee is,  accordingly, of  the view that as per the requirements of AS 16, borrowing costs related to construction of an asset incurred upto the time the asset is ready for its intended use, i.e., ready to commence commercial production, should be capitalised,  and,  thereafter,  all  borrowing  costs  should  be  charged  to revenue; the Standard does not recognise deferment of borrowing costs where  the  actual  commencement  of  commercial  production  is  delayed. Thus, to that extent AS 16 supersedes the Guidance Note. The Committee also notes that paragraph 9.5 of AS 10 is also superseded by AS 16 and accordingly, deferment of costs where commercial production gets delayed is also not permissible.

 

21. The  Committee  is  of  the  view  that  interest  on  working  capital  to fund the normal trial run also contributes to construction of plant as trial run activity is regarded as an activity which is necessary to prepare the asset  for  its  intended  use.  This  is  because  flaws  in  the  assets  noticed during trial run production are rectified to bring the plant to its intended use.  Thus,  in  the  view  of  the  Committee,  interest  on  working  capital during trial run should also be capitalised as per the requirements of AS 16, despite the recommendations to the contrary contained in the Guidance Note on Expenditure During Construction Period, that such interest can be  deferred  for  a  period  of  3  to  5  years  after  the  commencement  of commercial production.

 

D. Opinion

 

22. On the basis of the above, the Committee is of the following opinion on the issues raised in paragraph 11 :

(a)        Whether the plant can still be considered to be on trial run and the asset has been put to its intended use is a question of fact to  be  determined  in  accordance  with  the  factors  stated  in paragraph 18 above.

 

(b)        The borrowing costs incurred during the normal period of trial run should be capitalised.

 

(c)        In view of the requirements of AS 16, no borrowing costs can be treated as deferred revenue expenditure.

 

(d)        In view of the requirements of AS 16, no interest cost can be treated as deferred revenue expenditure to be amortised over 3 to 5 years. Paragraph 4.3 of the Guidance Note, to the extent,

it allows deferment of interest costs stands withdrawn.

 

(e)        The  interest  on  working  capital  incurred  during  the  normal period of trial run should be capitalised.

 

1 Opinion finalised by the Committee on 5.7.2001

2 The Institute of Chartered Accountants of India has issued a clarification, published in November 2001 issue of the Journal ‘The Chartered Accountant’, which provides as below:

“It may be noted that paragraph 9.5 of AS 10…. relates to “all expenses” incurred during the period. This expenditure would also include borrowing costs incurred during the said period. Since AS 16 specifically deals with the treatment of borrowing costs, the treatment provided by AS 16 would prevail over the provisions in this respect contained in AS 10, as the provisions of AS 10 are general in nature and apply to “all expenses”.