|
Query No. 15
Subject:
Combining and segmenting of construction
contracts.1
A. Facts of the Case
1. A company, which is a Government of India undertaking, is a
leading engineering and consultancy company in the field of
petroleum refineries, pipelines, oil and gas processing,
petrochemicals, offshore structures and platforms, ports and
terminals, metallurgy, fertilisers, power, highway and bridges,
airports and intelligent buildings and urban development.
2. A client in the process of setting up grass-root refinery invited the company to submit its offer for providing engineering
consultancy services.
3. The company submitted its offer for carrying out consultancy
services for setting up of refinery project under three proposals
namely Proposal A (Process Design, Environmental Impact
Assessment/ Rapid Risk Analysis, etc.), Proposal B (Project
Management Consultancy Services), Proposal C (Engineering,
Procurement, Construction Management Services) with price for
each such proposal totaling to Rs. 665 crore plus service tax as
applicable.
4. The client, vide its Letter of Acceptance (LOA) dated 22nd
November, 2006, awarded the work (copy of LOA has been
furnished by the querist for the perusal of the Committee) for
consultancy services comprising the scope of work as above at a
price of Rs. 606 crore plus service tax as under :
-- The work shall be bifurcated into two contracts to cover
the total scope of work.
-- The first contract will be for Rs. 21 crore for the work of
defined preparatory services to be rendered between
1st September, 2006 and 31st March, 2007.
-- The balance price of Rs. 585 crore for the remaining
scope of work will form part of the second contract
which will be entered into at a later date. The first contract
will be suitably referenced in the second contract.
5. The first contract for Rs. 21 crore was formally entered into,
the work was executed and full payments were received. (Copy of
the contract has been furnished by the querist for the perusal of
the Committee.)
6. According to the querist, contract revenue for the year ending
31st March, 2007 was recognised as per the provisions of
Accounting Standard (AS) 7, Construction Contracts , treating the
above two contracts as a single construction contract for Rs. 606
crore in terms of paragraph 8 of AS 7. The total consideration for
overall project was negotiated as a single package with total cost
and overall profit margin for total price at Rs.606 crore. The bifurcation of fees in Part I and II was purely based on commercial
considerations without any relevance to the corresponding cost of
the each part. Since the nature of transactions satisfied all the
conditions as mentioned in paragraph 8 of AS 7, the same was
treated as a single contract for accounting purposes in the financial
year 2006-07. Accounts for the year 2006-07 were approved by
the Board on 30th May, 2007.
7. Pending finalisation and signing of the second contract, an
interim agreement/ arrangement was entered into on 15th May,
2007 with effect from 1st April, 2007 to provide uninterrupted
services within the scope of work forming part of the second
contract, wherein a lump sum amount of Rs. 7 crore plus applicable
taxes was paid to the company per month for a period of four
months for the defined scope of work. The interim arrangement
was for a period of 4 months or signing of the contract II, whichever
earlier. (Copy of the interim arrangement agreement has been
furnished by the querist for the perusal of the Committee.) As per
the interim arrangement, the activities covered under the said
arrangement shall be a part of contract II and the payments made
under this interim arrangement shall be adjusted against the lump
sum price of contract II, i.e., Rs. 585 crore.
8. The above interim arrangement was further extended for a
month till 31st August, 2007, pending finalisation/ signing of the
second contract. All payments under the interim arrangement, i.e.,
Rs. 35 crore (Rs. 7 crore * 5) and applicable taxes have since
been received. This interim arrangement was neither extended
beyond August, 2007 nor was contract II signed.
9. Meanwhile, in July/August, 2007 the client invited fresh
proposal from various consultants including the company for
providing consultancy services to execute the refinery project for
prospective services with new methodology and terms. Accordingly,
proposal dated 2nd August, 2007 and 6th August, 2007 were
submitted to the client for providing the desired services, detailing
the methodology of work execution, terms and conditions and
remuneration for its services totalling to Rs. 970.53 crore. (Copies
of proposals have been furnished by the querist for the perusal of
the Committee.)
10. The company, after negotiations, submitted its final offer along
with justification amounting to Rs. 773.50 crore vide its Term Sheet
dated 25th October, 2007 (copy of the Term Sheet has been
furnished by the querist for the perusal of the Committee)
The price of Rs.773.50 crore was arrived at as below:
(a) Base price agreed : Rs.635.5 crore (i.e., midpoint
between Rs.606 crore and Rs.665 crore)
(b) Add: Escalation (as proposed by the company): Rs.128
crore
(c) Less: Price paid by the client : Rs. 25 crore (although
Rs.56 crore has been invoiced).
(d) Add: extra price for changed terms : Rs.15 crore
(e) Add: extra price for FEED package:Rs.20 crore
Total price : Rs.773.50 crore
The querist has informed that though the company has received
the total amount of Rs.56 crore as invoiced, only Rs.25 crore has
been offered as reduction against the same (in the justification for
increase in the fees) as some part of the work done earlier would
need to be redone due to change in methodology for completing
the balance work.
The escalation of Rs.128 crore was sought as increase in fees for
the overall project due to delays on the part of the client in
implementation of the project and the consequent increase in the
cost to the company for the job. Thus, it was for increase in fees
from the originally quoted/agreed consideration i.e., Rs.665 crore /
Rs.606 crore respectively for the total execution of the project
covering Part I/interim arrangement/balance work.
The changed terms for which Rs.15 crore was proposed mainly
cover changes in the time schedule for the completion of the
project and related bonus/penalties, additional terms of
guaranteeing the estimated project cost, consequent penalty, etc.
11. The client accepted the company s final offer and issued LOA
dated 14th November, 2007 specifying the scope of work and
remuneration for prospective services to be rendered for the project
with a project completion schedule of 42 months from the date of
LOA. (Copy of the final offer and LOA dated 14th November, 2007
have been furnished by the querist for the perusal of the
Committee.)
The aforesaid LOA contained the following clause:
All other terms & conditions will be in line with the draft
contract PRP/EPCM/001B dated March 23, 2007 except for
amendments required in the contract which both parties shall
mutually agree.
The draft contract mentioned above is intended for Part II of earlier
LOA dated 22.11.2006 for Rs.606 crore.
12. The querist has informed that all other consultants had given
their price and terms for the total project/jobs without considering
the scope of the work completed by the company. However,
depending on the acceptability of the portion of the engineering
work already completed by the company upto the date of award of
the work, other consultants could have given some discounts on
the price which is not ascertainable. If at any stage, the client
wants to discontinue the services of a consultant, balance portion
could be contracted to other consultants and in that case the
consultant may be required to redo the substantial work to make it
compatible with their methodology of project execution and give
their terms accordingly.
13. Further, the querist has informed that in the event a
consultant s job is discontinued at the mid stage, the contract
needs to be terminated. As per the querist, in the instant case
though LOA dated 22nd November, 2006 was in place, since there
was no formal contract with the company for the Part II of the job,
probably the question of termination of contract would not apply
and the company would have only received the payments for the
first part and interim arrangement totaling Rs.56 crore.
14. As per the querist, cost has been estimated for the total job involved in execution of the project and proposal submitted to the
client accordingly. As such no separate costing has been done for
part I, II/balance work. As mentioned in paragraph 6 above, the
bifurcation of the fees in the Part I and balance portion of work
was purely on commercial consideration without estimating and
considering the cost separately. However, estimated cost for the
balance portion of the job can be ascertained taking into account
the cost already incurred for completed portion of the job under
Part I/interim arrangement.
15. The querist has given the following arguments for combining
as well as segmenting contracts:
Alternative I- For combining contracts
New LOA dated 14.11.07 for prospective services is to be
considered as group of contracts along with earlier contract/
arrangement in terms of paragraph 8 of AS 7 due to the
under noted reasons:
(a) The scope of services remained the same as were
envisaged in the original LOA dated 22.11.2006 with
some changes in the price due to escalation factor and
some additional scope of work and changes in
methodology of execution. As such, this should be
construed as an extension of the original job which is
also referred in the term-sheet dated 25.10.07 submitted
by the company and forming part of LOA dated 14.11.07.
Hence, LOA dated 14.11.07 should be construed as renegotiation
of the price and terms due to temporary
withholding of the job. [The querist has clarified that the
additional scope and change in methodology of execution
are not significantly different from what was originally
contemplated.]
(b) The scope of services pursuant to earlier LOA as well
as new LOA pertains to construction of same asset and
activities contemplated under the project are also
primarily the same except for some modifications/
additions/deletions in the scope of work. The price of
the services has been negotiated with reference to the original LOA terms and remuneration taking into account
the services already rendered and as such all the
contracts/arrangement are inter-related and are part of
a single project with overall profit margin. Further, the
term escalation used in the term-sheet dated 25.10.07
submitted by the company can be construed with
reference to existing contract or an already negotiated
consideration.
(c) LOA dated 14.11.07 stipulates that All other terms &
conditions will be in line with the draft contract PRP/
EPCM/001B dated March 23, 2007 except for
amendments required in the contract which both parties
shall mutually agree. [Emphasis supplied by the querist.]
Alternative II-For segmenting contracts
Work done pursuant to earlier LOA/Contract/interim
arrangements against which the company had rendered
services and received payment of Rs.56 crore should be
treated as a separate construction contract in view of the
following observations:
(a) The services in accordance with earlier LOA/interim
arrangement have been rendered and full payments
received.
(b) Client has obtained separate offer from various
consultants including the company for prospective
services of the project with certain modifications including
additional scope and change in execution methodology.
The company had submitted its offer against the same
which has been accepted and LOA has been issued for
prospective services only and fresh contract for such
services should be entered into.
B. Query
16. The querist has sought the opinion of the Expert Advisory
Committee as to whether the amount of Rs. 56 crore received
from the client for the services rendered under the earlier contract/ interim arrangements (which have since been closed) can be
recognised as revenue in the books of account of the company
considering them as a separate construction contract, distinct and
separate from scope of work under LOA dated 14th November,
2007 for Rs. 773.50 crore in compliance with the provisions of AS
7.
C. Points considered by the Committee
17. The Committee notes that the basic issue raised by the querist
relates to the treatment of the receipt of Rs. 56 crore as revenue
from a separate contract de hors the balance scope of work under
the subsequent LOA dated 14th November, 2007. Therefore, the
Committee has examined only this issue and has not examined
any other issue that may be contained in the Facts of the Case. In
particular, the Committee has not examined the issue whether the
LOA dated 14th November, 2007 itself is to be segmented for
scope change, since this issue has not been raised by the querist.
The Committee notes from the copies of documents furnished by
the querist that the amount of Rs. 773.50 crore includes, inter alia,
(i) an amount of Rs. 52 crore towards services of the company in
respect of crude oil receipt facilities at Mundra and cross country
crude oil pipeline from Mundra to Bhatinda and in case the client
excludes services related to these two items from the scope of
work awarded to the company, then, a reduction of Rs. 52 crore
will be made from the lump sum price of Rs. 773.50 crore and (ii)
an amount of Rs. 20 crore towards FEED package. Though the
item (i) consisting of the two facilities is also found in the original
scope of work, it appears that no specific price is mentioned for it
in the original scope of work. (Of course, the client has the right to
request for any changes, modifications, deletions and/or deletions
to the scope of work for which impact proposal should be
submitted by the company, if the changes can be performed). The
Committee has not addressed the issue of treatment of these
elements of contract, since this issue has not been raised by the
querist.
18. The Committee notes that Accounting Standard (AS) 7,
Construction Contracts, issued by the Institute of Chartered
Accountants of India has subsequently been notified by the Central Government under the Companies (Accounting Standards) Rules,
2006. The Committee notes the following paragraphs from AS 7:
2.1 A construction contract is a contract specifically
negotiated for the construction of an asset or a
combination of assets that are closely interrelated or
interdependent in terms of their design, technology and
function or their ultimate purpose or use.
3. A construction contract may be negotiated for the
construction of a single asset such as a bridge, building, dam,
pipeline, road, ship or tunnel. A construction contract may
also deal with the construction of a number of assets which
are closely interrelated or interdependent in terms of their
design, technology and function or their ultimate purpose or
use; examples of such contracts include those for the
construction of refineries and other complex pieces of plant or
equipment.
4. For the purposes of this Standard, construction contracts
include:
(a) contracts for the rendering of services which are
directly related to the construction of the asset, for
example, those for the services of project managers
and architects; and
(b) ..."
6. The requirements of this Standard are usually applied
separately to each construction contract. However, in certain
circumstances, it is necessary to apply the Standard to the
separately identifiable components of a single contract or to a
group of contracts together in order to reflect the substance
of a contract or a group of contracts.
7. When a contract covers a number of assets, the
construction of each asset should be treated as a separate
construction contract when:
(a) separate proposals have been submitted for each
asset;
(b) each asset has been subject to separate
negotiation and the contractor and customer
have been able to accept or reject that part of
the contract relating to each asset; and
(c) the costs and revenues of each asset can be
identified.
8. A group of contracts, whether with a single customer
or with several customers, should be treated as a single
construction contract when:
(a) the group of contracts is negotiated as a single
package;
(b) the contracts are so closely interrelated that they
are, in effect, part of a single project with an
overall profit margin; and
(c) the contracts are performed concurrently or in
a continuous sequence.
9. A contract may provide for the construction of an
additional asset at the option of the customer or may be
amended to include the construction of an additional
asset. The construction of the additional asset should be
treated as a separate construction contract when:
(a) the asset differs significantly in design,
technology or function from the asset or assets
covered by the original contract;or
(b) the price of the asset is negotiated without
regard to the original contract price.
Contract Revenue
10. Contract revenue should comprise:
(a) the initial amount of revenue agreed in the
contract; and
(b) variations in contract work, claims and incentive
payments:
(i) to the extent that it is probable that they will
result in revenue; and
(ii) they are capable of being reliably measured.
11. Contract revenue is measured at the consideration
received or receivable. The measurement of contract revenue
is affected by a variety of uncertainties that depend on the
outcome of future events. The estimates often need to be
revised as events occur and uncertainties are resolved.
Therefore, the amount of contract revenue may increase or
decrease from one period to the next. For example:
(a) a contractor and a customer may agree to variations
or claims that increase or decrease contract revenue
in a period subsequent to that in which the contract
was initially agreed;
(b) the amount of revenue agreed in a fixed price
contract may increase as a result of cost escalation
clauses;
(c) the amount of contract revenue may decrease as a
result of penalties arising from delays caused by
the contractor in the completion of the contract; or
(d) ..."
19. From the above, the Committee notes that the principles related
to accounting treatment for construction of an asset (including
combining and segmenting of construction contracts) are equally
applicable to services directly related to the construction of that
asset. Hence, engineering consultancy services and other services
which are directly related to the construction of the refinery will be
accorded the same accounting treatment as the treatment for the
construction contract of the refinery.
20. The Committee notes that for accounting purposes, initially
the company combined the two contracts, viz., preparatory services
(for which contract was signed) and the balance scope of work
(which was supposed to be entered into later). There was an
interim arrangement pending the signing of second contract. This interim arrangement makes appropriate reference to the second
contract to be entered into in future. While the work under the
interim arrangement was in progress, the client invited fresh
proposal from various consultants including the company for
providing consultancy services to execute the refinery project with
new methodology and terms. After negotiation, the price for the
balance scope of work (excluding for the work already completed)
was arrived at by the company, which was accepted by the client.
Invitation of fresh bids and separate LOA dated 14th November,
2007 with net price for balance scope of work may apparently
suggest that the scope of the original contract has been reduced
to the extent of work already done and that the balance scope of
work is a separate contract, though the latter includes pending
portion of original scope (which is substantial for the facts of the
case) with some changes. However, for accounting purposes,
whether the balance scope of work is to be treated as a separate
contract or to be combined with earlier contract/interim arrangement
with scope reduced to the extent of work already done depends
on application of relevant provisions of AS 7 quoted above and not
on legal aspects.
21. The Committee is of the view that in the present case,
paragraph 7 of AS 7 is not applicable since it is not a case of
single contract covering a number of assets with separate proposals
for each asset. While paragraph 8 of AS 7 does not directly deal
with a case where during the course of execution of a contract
fresh bidding takes place resulting in a new contract for balance
scope of work, the Committee is of the view that the principle
enshrined in paragraph 8 of AS 7 can be applied as a guiding
factor in such situations. The Committee is also of the view that a
group of contracts should be combined if all the three conditions
stipulated in paragraph 8 of AS 7 are met, and, should not be
combined if any one or more of the three conditions stipulated
therein are not met. This is because paragraph 8 of AS 7 uses the
word and at the end of condition (b).
22. The Committee notes that basically the consultancy services
are in respect of construction of a refinery. There is only change in
the methodology of execution of the project with some scope change and not the asset being constructed. The asset is still
refinery. All the bidders had based their price for the entire work
and the successful bidder was expected to discount the price on
the assessment of the work already done by the company. The
company too started from the base price and made some
adjustments to arrive at the price for the balance scope of work.
Thus, the balance scope of work is not separately negotiated
without regard to the original contract/interim arrangement. This is
fully supported by the facts mentioned in paragraph 10 above. For
example, the escalation element is not only for the balance scope
of work but for the entire project. Though Rs. 56 crore was billed
and accepted, only Rs.25 crore was reduced from the base price
since the company has to redo some part of work done earlier due
to change in methodology for completing the balance work. As
mentioned in paragraph 14 above, no separate costing was done
for original contract/interim arrangement/balance scope of work.
Cost was estimated for the total job involved in the execution of
the project. Price was allocated to each such part purely on
commercial consideration without estimating and considering the
cost separately. While estimation for balance work could have
been done not separately but after considering cost already
incurred, that has not been done. This indicates that only overall
profit margin has been contemplated at all stages. The balance
scope of work, when undertaken as a continuation of work already
done, will complete the whole project. The LOA dated 14th
November, 2007 also specifies that all other terms and conditions
are as per draft of the originally contemplated second contract,
except for mutually agreed amendments. The Committee is of the
view that all these facts indicate compliance with conditions
stipulated in paragraph 8 of AS 7.
23. From the above, the Committee is of the view that the original
contract, the interim arrangement and the LOA dated 14th
November, 2007 for balance scope of work are interconnected
and should be treated as such for accounting purposes. The entire
services are related to the construction of the refinery, though
there is change in methodology of execution and there are some
scope changes. Further, the Committee is of the view that the
paragraph 10(b) of AS 7 is applicable whether it is a single contract
or a group of contracts treated as a single contract for accounting purposes. Accordingly, the difference between (a) the price for
balance scope of work as increased by Rs.25 crore offered as
reduction in respect of work already done and (b) the original
contract price should be viewed as contract revenue towards
variations in the contract work, claims and incentive payments
mentioned in paragraph 10(b) of AS 7 quoted above. Paragraph
11(a) of AS 7 quoted above acknowledges that a contractor and a
customer may agree to variations or claims that increase or
decrease contract revenue in a period subsequent to that in which
the contract was initially agreed. The Committee is of the view that
this variation can happen even in the case of fresh bidding process
as has happened in the present case. In working out the aforesaid
variations and claims, the point whether the LOA dated 14th
November, 2007 itself is to be segmented for accounting purposes
in respect of scope changes (such as additional scope of work
relating to services of the company in respect of the items
mentioned in paragraph 17 above) should also be considered. For
the reasons stated in paragraph 17 above, the Committee is not
expressing any view in this regard.
24. With respect to the part of the work done earlier in respect of
which the amount of Rs. 56 crore has already been received, the
Committee is of the view that Rs. 25 crore represents the work to
be adjusted in the final offer and, therefore, the portion amounting
to Rs. 31 crore {i.e., Rs. 56 crore received less: Rs. 25 crore}
which is separated from the final offer, should be booked as
revenue.
D. Opinion
25. On the basis of the above, the Committee is of the opinion
that out of the amount of Rs.56 crore received from the client for
the services rendered under the earlier contract/interim
arrangements, Rs. 25 crore cannot be separately recognised as
revenue considering them as a separate construction contract
distinct and separate from the scope of work under LOA dated
14th November, 2007 for Rs. 773.50 crore. However, the balance
portion of Rs. 31 crore should be recognised as revenue
separately.
1 Opinion finalised by the Committee on 30.5.2008 |