| Item (A) |
Rs. 17.68 crore incurred and booked as
expenditure. The remaining portion of expenditure
will be booked according to the accounting policy
of the company, as and when the land is acquired. |
| Item (B) (C)& (D) |
Rs. 4.89 crore has been incurred and accounted
for, and accounting for further expenditure shall be
made as and when the company’s obligation
(contractual/legal) shall arise. |
The querist has also clarified that while no specific agreement was
entered into with village panchayats, an amount of Rs. 1250 lakh
would be spent on the infrastructure works of various villages/
panchayats on the basis of the plan approved and sent by different
panchayats. This is included in the amount of Rs. 2,353 lakh for
item (D) above.
6. The Government auditors, during the review of accounts of
the company, had commented that ‘Capital Work in Progress
(CWIP) – Incidental Expenditure During Construction’ and ‘Current
Liabilities & Provisions’ were understated due to short provision of
Rs 30.90 crore due to non-providing of balance amount of Rs.
30.90 crore being the difference between the rehabilitation and
resettlement cost approved by the Board (Rs. 53.47 crore) and the
expenditure accounted for up to 31.03.2007 amounting to Rs.
22.57 crore (Rs. 17.68 crore and Rs. 4.89 crore) in the books.
7. The company, in its reply to the auditors, had stated that the
rehabilitation and resettlement cost approved by the Board was an
estimated cost for the entire duration of the project which may change ((+)/(-)) depending on the actual requirement. The
expenditure incurred upto 31.03.2007 had already been accounted
for. Further expenditure can be booked only after goods/services
have been received by the company or the company, by virtue of
contractual/legal obligation, is required to incur the expenditure
and not merely based upon approved plans. The work of the
project has just begun and no such event has occurred at the date
of balance sheet which has resulted in company’s obligation for
rehabilitation and resettlement beyond what has been accounted
for and no provision is required to be made for balance expenditure
which is yet to be incurred. It was agreed with the auditors to refer
the matter to the Expert Advisory Committee of the Institute of
Chartered Accountants of India for opinion.
8. The querist has quoted the following paragraph of Accounting
Standard (AS) 29, ‘Provisions, Contingent Liabilities and Contingent
Assets’:
“14. A provision should be recognised when:
(a) an enterprise has a present obligation as a result
of a past event;
(b) it is probable that an outflow of resources
embodying economic benefits will be required
to settle the obligation; and
(c) a reliable estimate can be made of the amount
of the obligation.
If these conditions are not met, no provision should
be recognised.”
The querist has also referred to paragraph 17 of AS 29, which,
inter alia, states that no provision is recognised for costs that need
to be incurred to operate in the future and that the only liabilities
recognised in an enterprise’s balance sheet are those that exist at
the balance sheet date. The querist has also referred to paragraph
18 of AS 29 which, inter alia, prescribes that it is only those
obligations arising from past events existing independently of an
enterprise’s future actions (i.e., the future conduct of its business)
that are recognised as provisions. Some examples are also given in Appendix C to AS 29 which illustrate the circumstances in which
provisions are required to be made. As per the querist, these
examples do not specifically cover the case of the company.
9. According to the querist, since no event has occurred which
may result in a present obligation, no provision was required to be
made at the balance sheet date (31.03.2007).
B. Query
10. In view of the above, the querist has sought the opinion of the
Expert Advisory Committee on the following issues:
(i) Whether the company is required to make a provision
for the balance of planned rehabilitation and resettlement
cost as explained above for which no contractual
obligation has arisen on the balance sheet date.
(ii) If the answer to the above is in the affirmative,
(a) whether the amount should be booked through
‘Incidental Expenditure During Construction (IEDC)’
or directly to capital work-in-progress.
(b) whether it also requires a change in the accounting
policy mentioned in paragraph 4(a) above.
C. Points considered by the Committee
11. The Committee notes that the basic issue raised by the querist
relates to the need for provision towards balance of planned
rehabilitation and resettlement cost. Therefore, the Committee has
examined only this issue and has not examined any other issue
that may be contained in the Facts of the Case, such as,
correctness of accounting policy of the company as reproduced by
the querist in paragraph 4(a) above in general, or appropriateness
of capitalisation of various expenses, e.g., those related to
afforestation, as part of cost of land, etc. The Committee has also
not examined the accounting policy of the company as reproduced
in paragraph 4(b) above, as that issue has not been raised by the
querist.
12. The Committee notes, from the copy of Resettlement and
Rehabilitation Scheme (R & R Scheme) for the project affected
families of ‘Y’ Hydro Electric Project furnished by the querist, that
the same has been made by the State Government and the
company pursuant to Rule 8-A of the HP Nautor Land Rules,
1968. Hence, in the view of the Committee, the obligations created
under the scheme are legal in nature.
13. The Committee notes paragraph 14 of AS 29 quoted by the
querist in paragraph 8 above and the following paragraphs from
AS 29:
“10.1 A provision is a liability which can be measured
only by using a substantial degree of estimation.
10.2 A liability is a present obligation of the enterprise
arising from past events, the settlement of which is
expected to result in an outflow from the enterprise of
resources embodying economic benefits.
10.3 An obligating event is an event that creates an
obligation that results in an enterprise having no realistic
alternative to settling that obligation.”
“10.6 Present obligation - an obligation is a present
obligation if, based on the evidence available, its existence
at the balance sheet date is considered probable, i.e.,
more likely than not.”
“11. An obligation is a duty or responsibility to act or perform
in a certain way. Obligations may be legally enforceable as a
consequence of a binding contract or statutory requirement.
Obligations also arise from normal business practice, custom
and a desire to maintain good business relations or act in an
equitable manner.”
“16. A past event that leads to a present obligation is called
an obligating event. For an event to be an obligating event, it
is necessary that the enterprise has no realistic alternative to
settling the obligation created by the event.
17. Financial statements deal with the financial position of
an enterprise at the end of its reporting period and not its possible position in the future. Therefore, no provision is
recognised for costs that need to be incurred to operate in the
future. The only liabilities recognised in an enterprise’s balance
sheet are those that exist at the balance sheet date.
18. It is only those obligations arising from past events
existing independently of an enterprise’s future actions (i.e.
the future conduct of its business) that are recognised as
provisions. Examples of such obligations are penalties or cleanup
costs for unlawful environmental damage, both of which
would lead to an outflow of resources embodying economic
benefits in settlement regardless of the future actions of the
enterprise. Similarly, an enterprise recognises a provision for
the decommissioning costs of an oil installation to the extent
that the enterprise is obliged to rectify damage already caused.
In contrast, because of commercial pressures or legal
requirements, an enterprise may intend or need to carry out
expenditure to operate in a particular way in the future (for
example, by fitting smoke filters in a certain type of factory).
Because the enterprise can avoid the future expenditure by
its future actions, for example by changing its method of
operation, it has no present obligation for that future
expenditure and no provision is recognised.
19. An obligation always involves another party to whom the
obligation is owed. It is not necessary, however, to know the
identity of the party to whom the obligation is owed – indeed
the obligation may be to the public at large.”
14. From the above, the Committee is of the view that a provision
cannot be recognised simply because there is an approved cost or
there is a legal or contractual obligation. A provision should be
made only if it fits within the parameters discussed in paragraph
13 above, apart from meeting the recognition criteria prescribed in
paragraph 14 of AS 29, reproduced by the querist in paragraph 8
above. In particular, provision should not be recognised before the
obligating event arises under the provisions of law or the terms of
contract.
15. As stated by the querist in paragraph 5 above, the approved
cost for rehabilitation and resettlement consists of cost of land, resettlement cost, rehabilitation cost and cost of area development/
community development. The Committee notes that the financial
plan furnished by the querist contains detailed list of various
expenses. As examples, likely obligating events for some items
are given below:
(i) So far as cost of land is concerned, the Committee is of
the view that acquisition of land is the obligating event.
Hence, if the land owner is yet to fulfill his obligation of
transferring the property in the land to the company, the
company has no present obligation to pay compensation
to the land owner. The Committee is, therefore, of the
view that until land is acquired, no provision should be
created in respect of the cost of land.
(ii) A published environmental policy of the company by
itself, does not create a legal or contractual obligation.
From the Facts of the Case and copies of documents
furnished by the querist, it is not clear as to whether
there is any legal or contractual obligation for
afforestation, compensatory afforestation, soil
conservation and reforestation towards forest land. In
case there is any legal or contractual obligation for
compensatory afforestation, felling of existing trees or
even acquisition of land could be the obligating event
depending on the provisions of law or the terms of the
contract.
(iii) Acquisition of land is the obligating event triggering the
provision for resettlement grant payable to the concerned
project affected family.
The Committee is of the view that the obligating events for other
items should similarly be identified before recognising any provision.
16. On the basis of the above, the Committee is of the view that
provision should be made as soon as the obligating event arises
provided it also meets the other recognition criteria stated in
paragraph 14 of AS 29. The amount of the provision would depend
on the extent of the obligation arising from the obligating event
rather than being made for the entire difference between the approved cost and actual expenditure incurred. The approved cost
could be used as the basis for estimating the extent of the obligation
arising from the obligating event, i.e., the amount for which the
provision is to be recognised. As regards the company’s approach,
it is not clear as to whether the underlying obligating events were
identified and the recognition criteria were met in respect of
provisions recognised based on contractual/legal obligations and
whether all the provisions to be recognised on that basis have
been recognised for amounts as discussed above.
17. As regards capitalisation of the relevant items, the Committee
is of the view that it is to be decided based on the applicable
Accounting Standards, such as, Accounting Standard (AS) 10,
‘Accounting for Fixed Assets’. Thus, simply because an expenditure
is incurred during construction, it does not necessarily mean that
the said expenditure is eligible for capitalisation. If an expenditure
is not eligible for capitalisation, it should be expensed, unless
another accounting standard requires or permits a different
treatment.
18. A project may consist of several fixed and intangible assets.
The Committee is of the view that if an expenditure is eligible for
capitalisation, it should be accorded the following treatment:
(i) If the expenditure results in the acquisition of an asset,
it should be directly capitalised as part of the cost of
that asset. For example, cost of land should be directly
capitalised as ‘Land’. Similarly, resettlement grant
payable to the project affected families should be
capitalised as part of cost of land, since the land cannot
be acquired without incurring that expenditure.
(ii) If the expenditure is directly related to, or benefits, a
particular asset under construction, it should be booked
to ‘Capital Work in Progress’ and identified with the
relevant asset under construction. In establishing whether
the expenditure directly benefits or is related to an asset,
a nexus between the expenditure and the benefit/
relationship with the asset should be established
technologically. For example, compensation for damage
to private property due to blasting during construction should be booked to ‘Capital Work in Progress’, if the
blasting is done for the purpose of construction of a
particular asset.
(iii) If the expenditure is related to, or benefits, more than
one asset under construction, it should be booked to
‘Incidental Expenditure During Construction’ and
capitalised as part of the cost of the relevant assets
appropriately at the time of completing the exercise of
capitalisation. For example, compensation for damage
to private property due to blasting during construction
should be booked to ‘Incidental Expenditure During
Construction’, if the blasting is done for the purpose of
construction of more than one asset.
Thus, capitalisation of the relevant expenditure should be done on
the basis of the principles stated above when the expenditure is
incurred/provision is made in accordance with paragraph 16 above.
19. As regards the company’s accounting policy mentioned by
the querist in paragraph 4(a) above, the Committee is of the view
that subject to the considerations stated in paragraph 11 above,
the said policy of the company may require a change on the basis
of considerations discussed in paragraphs 17 and 18 above.
Further, while applying the accounting policy, the provision should
be recognised immediately when and to the extent the obligating
event takes place, and when the other recognition criteria for
provision are met.
D. Opinion
20. On the basis of the above, the Committee is of the following
opinion on the issues raised in paragraph 10 above:
(i) The company is not required to make a provision for
the balance of planned rehabilitation and resettlement
cost until in respect of the individual items of expenses,
the obligating event arises and the recognition criteria
are met.
(ii) (a) For treatment of expenditure, see paragraphs 17
and 18 above.
(b) As regards need for change in the company’s
accounting policy mentioned in paragraph 4(a)
above, see paragraph 19 above.