Expert Advisory Committee
ICAI-Expert Advisory Committee
Options:

Query No. 35.

Subject:

Treatment of expenditure during construction period.1

A. Facts of the Case

1. A company was incorporated in the year 2003. Its registered office is located in Tamil Nadu (TN). It has its project office and is constructing its first power project within the State. As on date, the company has no other branch/ unit and is a single project company. Further projects will be taken-up after another 2-3 years only. Construction activity will go on till the financial year 2010-11, when the commissioning activity will start. The commissioning activity/ stabilisation may take 6-8 months’ time and, hence, commercial operations are likely to start in the financial year 2011-12 only. Accordingly, as on date, there is no other operation and maintenance (O&M)/ revenue activity. The company, however, earns certain interest on bank deposits from time to time.

2. According to the querist, for such a long duration project, at times, there is a need to adopt more than one option/approach for a particular construction activity. Ultimately, it will be any one of those options which will finally be adopted and the rest may have to be abandoned in between due to circumstances, on which, some costs might have been incurred or the company may have to pay foreclosure costs.

3. The company has recruited certain manpower, traditionally called as O&M manpower. During construction phase, some of them have been sent on training for O&M. The O&M training is a long term activity and goes on for about a year. Even thereafter, they will be placed on ‘on the job activities’ in some operating unit or on some simulator. There being no watertight segregation, a few of the O&M appointees may be involved in the construction activities going on at present. The O&M staff needs to be qualified and licensed before commissioning activities are undertaken. It is then only that the regulators will give permission for commissioning activities to start. At that time, they all will be placed on activities related to commissioning and, thereafter, for O&M in due course. Without trained, qualified and licensed man power in place by the time of commissioning (which is routinely called/ known as O&M man power), commissioning is just not possible as regulatory clearances will not be forthcoming.

4. For such a long duration project, the company feels that it needs to have a conducive atmosphere within and around the project, because any disruption due to unrest from within or in the surroundings can cause delay in completion of the project, thereby causing more completion/ capital costs on the project. Removal of local fears and winning over confidence and support of locals are, therefore, prerequisites for timely completion of the project. With this objective and due approvals, the company plans to spend about Rs. 25 lakh every year for ‘Neighborhood Development’. This is used for construction of small infrastructure items in nearby villages, helping them for their education and health related activities. From the company’s view point, though the project is at the construction stage and has no revenue generating activities, this type of expenditure is unavoidable and has a long term advantage for the company.

5. Cost of the project in hand is about Rs. 3,500 crore. Whereas outlay during the financial year 2007-08 was Rs. 390 crore, the amount involved in the three points given in paragraph 6 below was Rs. 50.24 lakh, Rs. 36.79 lakh and Rs. 12.46 lakh, respectively. (So, according to the querist, materiality, perhaps, may not be there.)

6. The querist has stated that the auditor has raised a point as below:

       “…Statement of Expenditure during construction, pending allocation…includes Rs. 99.49 lakh in respect of the following items which are not represented by an asset in physical form :

                                                                                                                            Rs. in Lakh

           (i) Amount paid towards compensation for foreclosure of work
              order of shifting an equipment, using ‘strand jack system’.                       50.24
           (ii) Amount incurred on construction of community hall, compound
               wall of a school                                                                                     36.79
           (iii) Stipend paid to trainees.                                                                     12.46 
                Total                                                                                                    99.49
                                                                                                                        –––––––

           As the expenditure cannot be allocated to any asset, it should have been treated as ‘Miscellaneous Expenditure’, to be written off as ‘deferred revenue expenditure’ as and when the project is put into commercial operations and not as ‘Expenditure during construction , pending allocation’.

          Thus miscellaneous expenditure is understated with overstatement of ‘Expenditure during construction, pending allocation’ by Rs. 99.49 lakh.”

7. The company’s view for each of the item is as given below:


8. According to the querist, the company took into consideration the following:

       (i) Nature of its present activities – as stated in paragraphs 1 to 5 above.

       (ii) Guidance Note issued by the Institute of Chartered Accountants of India on Treatment of Expenditure during Construction Period, which also suggests that sometimes circumstances force a project to incur a capital expenditure which is not represented by any specific or any tangible asset and that in such cases, the expenditure so incurred would have to be treated in the books of account as capital expenditure and not as revenue expenditure.

     (iii) Accounting Standard (AS) 26, ‘Intangible Assets’, issued by the Institute of Chartered Accountants of India which, as per the querist, requires that deferred revenue expenditure incurred on or after 1st April, 2003, should be written off as current year expenses only.

9. As per the querist, keeping in view the points mentioned in paragraph 8 above, it was viewed by his professional colleagues that the three types of expenses (stated and detailed in paragraph 7 above) should be treated as ‘expenditure during construction’ and not as deferred revenue expenditure to be written off as and when the project is put into commercial operations. The company has accordingly treated the three types of expenses in its annual financial statements.

B. Query

10. The querist has sought the opinion of the Expert Advisory Committee on the following issues:

       (i) Whether the expenses stated and detailed in paragraph 7 above can be treated as ‘miscellaneous expenditure’, to be written off as ‘deferred revenue expenditure’ as and when the project is put into commercial operations.

      (ii) Whether it is correct/ fair to treat these expenses as ‘expenditure during construction, pending allocation’.

      (iii) Whether there is any other treatment and if so, it may be elaborated.

C. Points considered by the Committee

11. The Committee notes that the basic issue raised by the querist relates to the accounting treatment of the specific three types of expenses incurred during the construction period. Therefore, the Committee has examined only this issue and has not considered any other issue that may be contained in the Facts of the Case.

12. At the outset, the Committee wishes to point out that recommendations of a Guidance Note would be applicable only to the extent that they are not contrary to an Accounting Standard. Hence, the recommendations of the ‘Guidance Note on Treatment of Expenditure during Construction Period’2 may be considered, only if they are not contrary to an Accounting Standard. In particular, the Committee notes that for the accounting year under consideration viz. 2007-08, Accounting Standard (AS) 26, ‘Intangible Assets’, notified by the Central Government under the Companies (Accounting Standards) Rules, 2006 (the ‘Rules’) is applicable. Further, the Committee notes that a project may consist of several fixed tangible and intangible assets. The Committee is of the view that if an expenditure is eligible for capitalisation based on the applicable Accounting Standard, such as, Accounting Standard (AS) 10, ‘Accounting for Fixed Assets’, it should be accorded the following treatment:

       (i) If the expenditure results in the acquisition of an asset, it should be directly capitalised as part of cost of that asset.

       (ii) If the expenditure is directly related to, or benefits, a particular asset under construction, it should be booked to capital work in progress and identified with the relevant asset under construction. In establishing whether the expenditure directly benefits or is related to an asset, a nexus between the expenditure and the benefit/ relationship with the asset can be established technologically.

      (iii) If the expenditure is related to, or benefits, more than one asset under construction, it should be booked to ‘expenditure during construction’ and capitalised as part of cost of the relevant assets appropriately at the time of completing the exercise of capitalisation.

Further, the Committee is of the view that if an expenditure is not eligible for capitalisation, it should be expensed, unless another Accounting Standard requires or permits a different treatment.

Amount paid towards compensation for foreclosure of work order of shifting an equipment, using ‘strand jack system’

13. The Committee notes from the Facts of the Case that strand jack system was initially contemplated to save erection time in the absence of cranes. At the same time, since it requires regulatory approval, option for crane hiring/purchase was also pursued in parallel. Since the regulatory approval was taking time, it was decided to go for heavy duty crawler crane, leaving the option of strand jack system midway. In this connection, the Committee notes the following paragraphs from AS 10 notified under the ‘Rules’:

       “9.1 The cost of an item of fixed asset comprises ...any directly attributable cost of bringing the asset to its working condition for its intended use…

        9.2 Administration and other general overhead expenses are usually excluded from the cost of fixed assets because they do not relate to a specific fixed asset. However, in some circumstances, such expenses as are specifically attributable to construction of a project or to the acquisition of a fixed asset or bringing it to its working condition, may be included as part of the cost of the construction project or as a part of the cost of the fixed asset.

        9.3 The expenditure incurred on start-up and commissioning of the project, including the expenditure incurred on test runs and experimental production, is usually capitalised as an indirect element of the construction cost…”

       “10.1 In arriving at the gross book value of self-constructed fixed assets, the same principles apply as those described in paragraphs 9.1 to 9.53. Included in the gross book value are costs of construction that relate directly to the specific asset and costs that are attributable to the construction activity in general and can be allocated to the specific asset. Any internal profits are eliminated in arriving at such costs.”

        “20. The cost of a fixed asset should comprise its purchase price and any attributable cost of bringing the asset to its working condition for its intended use.

         21. The cost of a self-constructed fixed asset should comprise those costs that relate directly to the specific asset and those that are attributable to the construction activity in general and can be allocated to the specific asset.”


14. The Committee is of the view that compensation for foreclosure of the option of strand jack system is an expenditure incurred in stopping a particular course of action and is not directly attributable to bringing an asset (or the relevant assets) to its (their) working condition. On the basis of the principles of AS 10 quoted in paragraph 13 above in conjunction with the principles mentioned in paragraph 12 above, the Committee is of the view that such compensation is not eligible for capitalisation and the same should be expensed, since, a different accounting treatment is not required or permitted in any other Accounting Standard.

Amount incurred on construction of community hall, compound wall of a school

15. As regards the expenditure incurred on construction of community hall and compound wall to school, though the said expenditure might have avoided possible delay in construction/ completion of the project and possible cost overrun as stated by the company in paragraph 7 above, the said expenditure was not incurred for the purpose of construction of any asset(s) and/or for bringing the asset to its working condition for its intended use. The Committee notes that the main purpose of the expenditure is removal of local fears and winning over confidence and support of locals. As stated by the querist in paragraph 4 above, this has long term advantage for the company. The Committee is of the view that this is akin to expenditure incurred on internally generated goodwill. Relevant paragraphs of AS 26 are reproduced below:

       “35. Internally generated goodwill should not be recognised as an asset.

        36. In some cases, expenditure is incurred to generate future economic benefits, but it does not result in the creation of an intangible asset that meets the recognition criteria in this Standard. Such expenditure is often described as contributing to internally generated goodwill. Internally generated goodwill is not recognised as an asset because it is not an identifiable resource controlled by the enterprise that can be measured reliably at cost.”

        “55. Expenditure on an intangible item should be recognised as an expense when it is incurred unless:

              (a) it forms part of the cost of an intangible asset that meets the recognition criteria…; or

              ...”


16. From the above, the Committee is of the view that expenditure incurred on construction of community hall and compound wall to school should be expensed, since a different accounting treatment is not required or permitted in any other Accounting Standard for such expenditure.

Payment of stipend to trainees

17. As regards the stipend to trainees (O & M staff), the Committee notes from the Facts of the Case that a few of them may be involved in the construction activities going on at present. The Committee is of the view that to the extent the trainees are involved in construction activities, the stipend should form part of capital work in progress, if those activities are identifiable with a specific fixed asset, or ‘expenditure during construction, pending allocation’ if those activities are identifiable with more than one fixed asset, as the case may be. To the extent the trainees are not involved in construction during the period, the project is under construction, the stipend should be expensed, since, a different accounting treatment is not required or permitted in any other Accounting Standard for that expenditure. In particular, the Committee notes the following portion of paragraph 56 of AS 26 (read in conjunction with paragraph 55 of AS 26 quoted in paragraph 15 above).

          “56. …Examples of other expenditure that is recognised as an expense when it is incurred include:

           (a) …

          (b) expenditure on training activities;

          (c) …

         (d) …”

The Committee is of the view that the above paragraph 56 of AS 26 is applicable for all types of training and not restricted to general training of sales or other auxiliary/administrative staff. Though training may be necessary to get authorisation to commission the plant and to enable the plant to start commissioning operations, the training expenditure is not incurred for construction of any asset(s) and/or bringing the asset to its working condition for its intended use.

D. Opinion

18. On the basis of the above, the Committee is of the following opinion on the issues raised in paragraph 10 above:

       (i) The expenses stated and detailed in paragraph 7 above cannot be treated as ‘miscellaneous expenditure’, to be written off as ‘deferred revenue expenditure’ as and when the project is put into commercial operations.

       (ii) It is not correct/fair to treat these expenses as ‘expenditure during construction, pending allocation’, except for stipend paid to trainees involved in construction activities when those activities are identifiable with more than one fixed asset.

       (iii) Compensation for foreclosure of work order for strand jack system, expenditure incurred on construction of community hall, etc. and stipend paid to trainees not involved in construction activities should be expensed. Stipend to trainees involved in construction activities should form part of capital work in progress, if those activities are identifiable with a specific fixed asset, or ‘expenditure during construction period, pending allocation’ if those activities are identifiable with more than one fixed asset.


1 Opinion finalised by the Committee on 09.01.2009

2 The Guidance Note on Treatment of Expenditure during Construction Period has been withdrawn by the Council of the Institute of Chartered Accountants of India vide its decision at its 280th meeting held on August 7-9, 2008.

3 To be read as 9.4.